Community Budget Issue Requests - Tracking Id #635FY0102 |
|||||||||
Homestead - Flood Mitigation Projects |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Curt Ivy |
Organization: |
City of Homestead |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Homestead - Flood Mitigation Projects |
Date Submitted: |
1/14/2002 6:06:28 PM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Ken Sorensen |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
Capital Outlay initiative |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
City of Homestead |
|
Contact: |
Mike Shehadeh, PE |
|
||||
|
790 North Homestead Blvd. |
|
Contact Phone: |
(305) 247-1801 101 |
|
||||
|
|
Homestead 33030 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Dade |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
Storm water hydraulic modeling; construct new and upgrade drainage elements; landscaping and R/W enhancemnent to prevent flooding; stormwater GIS system; portable pumps; 3 pump stations; track hoe; stormwater telemetry system; culvert removal at Keys Gate; grading; vegetation work & maint. equipment; canal/ditch/culvert cleaning & dredging; improvement to critical department buildings that are below flood level to prevent flooding. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
This will help advance the City's goals for mitigating the hazards of South Miami-Dade County flood problems. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$4,705,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Identify items(s) in the FY 2002-03 Appropriations Bill to be reduced: |
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation #: |
1748 |
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation Title: |
Statewide Restoration Projects |
||||||||
|
|
|
|
|
|
|
|
|
|
Amount to be reduced: |
$4,705,000 |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$4,705,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
None |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
City of Homestead Storm Water Master Plan |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
No |
|
|||||||
|
|
|
|
|
|
|
|
|
|