Community Budget Issue Requests - Tracking Id #181FY0102 |
|||||||||
Transit Coaches |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Byron Brooks |
Organization: |
Central Florida Regional Transportation Authority |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Transit Coaches |
Date Submitted: |
1/15/2002 11:24:43 AM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Andy Gardiner |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
Statewide goals are supported because of the project's contribution to addressing the capacity needs of the I-4 corridor and the I-4 Master Plan. Increased capacity and service expansion critically needed to address community transportation options. LYNX will need additional buses to meet its projected growth over the next five years. LYNX currently operates an express service in the I-4 corridor and the reconstruction of I-4 will place additional demand on the transit system and require additional vehicles to move traffic off the road and to help mediate the impact of construction. Service expansions, funded by our local governments, and route improvements have required LYNX to expedite its acquisition of additional buses in order to meet this demand. In addition, maintaining current levels of service has required the use of existing and newly purchased vehicles. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Central Florida Regional Transportation Authority |
|
Contact: |
Frankie Callen |
|
||||
|
445 West Amelia Street Suite 800 |
|
Contact Phone: |
(078) 413-1153 064 |
|
||||
|
|
Orlando 32801-1128 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Orange |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
In FY 2003 LYNX has programmed the purchase of 37 new buses for service expansion and route improvements. I-4 is planned for various improvements from FY 2002 to 2009. To alleviate the congestion that motorists will experience, LYNX is proposing to purchase additional transit coaches to implement express service on and adjacent to I-4. Currently, LYNX has 2 express service routes. Link 200 is express service from Volusia County to Downtown Orlando and Link 101 is express service from the West Oaks Mall in Ocoee to the University of Central Florida campus. The proposed express services most likely will run parallel to I-4 on John Young (including the extension through Ben White, 17-92, the Greenway and the Western Beltway). By summer of 2004, the Regional Intermodal Center will be fully operational and will enhance the expanded route network due to increase in operating capacity downtown and close proximity to I-4. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
Increased operational efficiencies, additional jobs. I-4 is a major freight and transportation corridor. Due to the proximity of the Orlando International Airport, Port Canaveral and the themed attractions to the tri-county area, the I-4 corridor is vital to the movement of goods and motorists. The reconstruction of the I-4 corridor will cause an interruption in the movement of those goods and motorists. The intent is to provide an alternative mode by offering better and efficient transit service, before, during, and after the construction. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$4,000,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Identify items(s) in the FY 2002-03 Appropriations Bill to be reduced: |
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation #: |
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation Title: |
|
||||||||
|
|
|
|
|
|
|
|
|
|
Amount to be reduced: |
$ |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$10,545,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
Local, Federal |
|
|||||||
|
Cash Amount: |
$6,545,000 |
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
Yes |
|
||||||
|
Amount: |
$4,000,000 |
|
|
|
|
|
||
|
Purpose for future year funding: |
|
annual requirements |
|
|||||
|
Will this be an annual request? |
|
|
Yes |
|
|
|||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
No |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
FDOTApproved-LYNX Transp. Development Plan,State Work Program&METROPLAN Orlando Transp. Improv. Plan |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Orange County Legislative Delegation meeting |
|||||||
|
Meeting Date: |
11/19/2001 |
|||||||
|
|
|
|
|
|
|
|
|
|