Community Budget Issue Requests - Tracking Id #164FY0102 |
|||||||||
Capital Circle NW/SW Airport to U.S. 90 |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Leon County |
Organization: |
Leon County Bd of Cty Commissioners |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Capital Circle NW/SW Airport to U.S. 90 |
Date Submitted: |
1/10/2002 1:06:12 PM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Curtis Richardson |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
The Long Range Transportation Plan for Tallahassee and Leon County indicates that this roadway needs to be widened to a four-lane facility. This will provide a much needed intermodal connection between the Tallahassee Regional Airport and Interstate 10, a major interstate highway connecting the west coat and the east coast of the United States. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Leon County |
|
Contact: |
Collen Roland or Don Lanham |
|
||||
|
301 South Monroe Street |
|
Contact Phone: |
(850) 891-8623 |
|
||||
|
|
Tallahassee 32301 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Leon |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
Capital Circle, Northwest/Southwest is a regionally significant roadway connecting the Tallahassee Regional Airport to Interstate 10. The segment of this roadway from US 90 to I-10 is currently under design with funding committed for right of way acquistion. The remainder of this roadway from the Tallahassee Regional Airport to Tennessee Street is five miles long and is currently a two-lane road. The project is estimated to cost approximately thirty millon dollars. The cost breakdown for the various phases of this project is as follows: > Project Development and Environment Study $2,500,000 > Design $2,500,000 > Right of Way Acquisition and Construction $25,000,000 |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
The improvement of this section would compliment the other phases of this project. It is believed that once complete, the enhanced transportation along with scheduled airport improvements will create freight related opportunities, creating new jobs. This improvement will also stimulate the creation of new jobs at Innovation Park, a high tech business park located west of the airport. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$30,000,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Identify items(s) in the FY 2002-03 Appropriations Bill to be reduced: |
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation #: |
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation Title: |
|
||||||||
|
|
|
|
|
|
|
|
|
|
Amount to be reduced: |
$ |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$62,800,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
Local |
|
|||||||
|
Cash Amount: |
$32,800,000 |
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
No |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
Tallahassee/Leon County Comprehensive Plan, Long Range Transporation Plan and Blueprint 2000 |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Leon County Board of County Commissioners |
|||||||
|
Meeting Date: |
7/31/2001 |
|||||||
|
|
|
|
|
|
|
|
|
|