Community Budget Issue Requests - Tracking Id #1541FY0102 |
|||||||||
City of Fernandina Beach - Water Supply Construction |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Jim Higginbotham |
Organization: |
City of Fernandina Beach |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
City of Fernandina Beach - Water Supply Construction |
Date Submitted: |
1/18/2002 11:01:46 AM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Aaron Bean |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
The conservation and more efficient usage of water; protection of the environment. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
City of Fernandina Beach |
|
Contact: |
Jim Higginbotham |
|
||||
|
1180 South 5th Street Extention |
|
Contact Phone: |
(904) 277-7380 |
|
||||
|
|
Fernandina Beach 32034 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Nassau |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
This project involves the construction of a reuse transmission system from the City of Fernandina Beach Wastewater Treatment Plant to the Rayonier Paper Mill. The proposed reuse transmission system will convey 2 million gallons per day (MGD) of reuse at startup and 4.25 MGD of reuse at build-out to the Rayonier Paper Mill to replace groundwater currently being utilized for cooling water in the mill process. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
This project will conserve approximately 730 Million gallons of water per year at start-up and 1.55 Million gallons per year at build-out by replacing a withdrawal from the Floridan Aquifer with reclaimed water that would otherwise be disposed of in the Amelia River. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$751,250 |
||||||||
|
|
|
|
|
|
|
|
|
|
Identify items(s) in the FY 2002-03 Appropriations Bill to be reduced: |
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation #: |
1748 |
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation Title: |
Grants & Aids to Local Govts. & Nonstate Entities - Fixed Capital Outlay - Statewide Restoration Projects |
||||||||
|
|
|
|
|
|
|
|
|
|
Amount to be reduced: |
$751,250 |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$751,250 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
None |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
Project Impact Evaluation by St. John's River Water Management District |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Nassau County Legislative Delegation |
|||||||
|
Meeting Date: |
9/26/2001 |
|||||||
|
|
|
|
|
|
|
|
|
|