Community Budget Issue Requests - Tracking Id #1245FY0102 |
|||||||||
Okeechobee Wastewater Trust |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
George Long |
Organization: |
Okeechobee County Commission |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Okeechobee Wastewater Trust |
Date Submitted: |
1/18/2002 8:38:59 PM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Frank Attkisson |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
Support and augmentation of FDEP 303 list of endangered waters. (Lake Okeechobee, Taylor Creek and Nubbins Slough). Reduction of Phosphorus and Nitrogen loading. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Okeechobee Utility Authority |
|
Contact: |
Landon C Fortner |
|
||||
|
South Park Street & 5th Avenue |
|
Contact Phone: |
(863) 763-9460 |
|
||||
|
|
Okeechobee 34974 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Okeechobee |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
Continued removal of septic tanks, and failing package plants from the Lake Okeechobee riM canal and canals that lead into Lake Okeechobee. Project is located in a Rural Area of Critical Economic Concern as designated by the Governor, pursuant to Chapter 288.0636 |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
Reduction of phosphorus and nitrogen leading of water that go into Lake Okeechobee. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$1,700,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Identify items(s) in the FY 2002-03 Appropriations Bill to be reduced: |
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation #: |
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation Title: |
|
||||||||
|
|
|
|
|
|
|
|
|
|
Amount to be reduced: |
$ |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$3,050,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
Local |
|
|||||||
|
Cash Amount: |
$1,300,000 |
In-Kind Amount: |
$50,000 |
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
Yes |
|
||||||
|
Fiscal Year: |
2001 |
Amount: |
$1,300,000 |
|
||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
Unknown |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
Lake Okeechobee Protection Act and FDEP Regulation of Nitrogen and Phosphorus |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Okeechobee Utility Authority, Okeechobee Legislative Delegation and Okeechobee County Commission |
|||||||
|
Meeting Date: |
10/30/2001 |
|||||||
|
|
|
|
|
|
|
|
|
|