Community Budget Issue Requests - Tracking Id #1182FY0102 |
|||||||||
Water Quality Model Tool |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Miami-Dade County Miami-Dade County |
Organization: |
Miami-Dade County |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Water Quality Model Tool |
Date Submitted: |
1/18/2002 11:45:36 AM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Wilbert Holloway |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
The water quality model/tool, in combination with the hydrodynamic model will provide the capabilty of assesing effects from proposed water management modifications being investigated in various local regional planning activities (Central & South Florida Project Review Study, Lower East Coast Water Supply Plan, South Biscayne Bay Watershed Management Plan.) These tools are also essential element in developing freshwater flow and targets for the Bay. This project is an essential element in the development of the intergrated areawide land use and water management plan for the south Miami-Dade County watershed(a/k/a South Biscayne Bay Watershed Management Plan) required in Policy 11.G of the County's Comprehensive Development Master Plan. The development of this land use and water management plan is a critical elements in ongoing Federal and State ecosystem restoration efforts in that it will define the future land uses in southern Miami-Dade County, which are compatible with restoration efforts. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Miami-Dade County DERM |
|
Contact: |
Rana Brown |
|
||||
|
33 S.W. 2nd Avenue |
|
Contact Phone: |
(305) 375-2494 |
|
||||
|
|
Miami 33130 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Dade |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
A water quality assesment tool will be developed to stimulate the transport of contaminants (i.e, nutrients, metals) in Biscayne Bay. Miami-Dade County is currently the local sponsor with the U.S. Army Corps of Engineers in the development of a hydrodynamic model which will stimulate water circulation and salinities in Biscayne Bay. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
Resource Managers and planning agencies will initially benfit from the project due to an increased understanding of impacts upon Biscayne Bay associated with the CS&F Project. This will eventually translate into a benefit by the commercial and recreational users of the Bay due to improved management of the quantity and quality of stormwater released into the Bay. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$250,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Identify items(s) in the FY 2002-03 Appropriations Bill to be reduced: |
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation #: |
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Specific Appropriation Title: |
From General Revenue or an appropriate existing Trust Fund |
||||||||
|
|
|
|
|
|
|
|
|
|
Amount to be reduced: |
$250,000 |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$941,536 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Operations and Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
Local, Federal |
|
|||||||
|
|
|
In-Kind Amount: |
$691,536 |
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
Yes |
|
||||||
|
Fiscal Year: |
1999-2001 |
Amount: |
$250,000 |
|
||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
Yes |
|
||||||
|
Amount: |
$250,000 |
|
|
|
|
|
||
|
Purpose for future year funding: |
|
Non-recurring Construction |
|
|||||
|
Will this be an annual request? |
|
|
Yes |
|
|
|||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
Yes |
|
||||||
|
Agency: |
Environmental Protection, Department Of |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
Yes |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
U.S. Army Corps of Engineers reprt 11/95, South Florida Water Mgmt. District Report 11/95 |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Miami-Dade County Commissioners; Miami-Dade Delegation |
|||||||
|
Meeting Date: |
11/19/2001 |
|||||||
|
|
|
|
|
|
|
|
|
|