Community Budget Issue Requests - Tracking Id #232 |
Sewer Improvement Phase III |
|
Requester: |
Jimmy Hand, City Manager |
Organization: |
City of Blountstown |
|
Project Title: |
Sewer Improvement Phase III |
Date Submitted |
1/7/2003 11:21:41 AM |
|
Sponsors: |
Lawson |
|
Statewide Interest: |
To eliminate storm water inflow & infiltration into City's existing sewer collection system |
|
Recipient: |
City of Blountstown |
|
Contact: |
Jimmy Hand |
|
|
20591 Central Avenue West |
|
Contact Phone: |
(850) 674-5488 |
|
|
Blountstown 32424 |
|
Counties: |
Calhoun |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
Refurbishment of City's Sewer System See DEP Water Project Application iD# WW2002000 Under HB 851 |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
No |
|
Measurable Outcome Anticipated: |
59,400 feet of sewer line repairs/replacement
|
|
Amount requested from the State for this project this year: |
$7,130,000 |
|
Total cost of the project: |
$7,130,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
None |
|
Cash Amount |
$ |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Comprehensive Plan/FDEP Consent order |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
Blountstown City Council |
|
Hearing Meeting Date: |
11/12/2002 |